Project management and planning, Interface engineering design and Refurbishment of Power Systems and Substations

Recent Projects - Scottish Power Energy Networks - South

Various Primary Substations - Primary Substations. Scottish Power required the integration works to provide a fully functional design for the 11kV and 33kV switchgear installations, including protection, control equipment and ancillary equipment at their Bulk Supply Points, primary substations and switching stations. For this work full circuit design was provided to the 33kV switchgear manufacturer for the development of standard solutions, this also included full mappings for IEC 61850 communications required from the various suppliers relays to the SCADA RTU, also of which were from different manufacturers, the projects also now encompassed the 11kV switchboards into IEC 61850 communication network.